What's due for your building, and when
Pick the systems you have and when they were last inspected. You'll see the next twelve months, so you can book everything together.
The planner needs JavaScript. You can still request service or call 1-833-344-3473.
Timing follows the National Fire Code and the standards it names: every 12 months for most systems, every 6 months for kitchen suppression and dry chemical systems. Monthly checks you do yourself aren’t shown. Your local fire department has the final say for your building.
The requirements, by province
All four provinces build their fire codes on the National Fire Code of Canada 2020, and Part 6 sends inspection work to the same standards. The intervals below apply in each province; the article numbers are the same in the national code and Alberta's edition.
- Alberta: National Fire Code – 2023 Alberta Edition, in force since 1 May 2024.
- British Columbia: BC Fire Code 2024, based on the National Fire Code 2020, in force since 8 March 2024. The City of Vancouver has its own fire by-law.
- Saskatchewan: National Fire Code of Canada 2020, through The Fire Safety Regulations, in force since 1 January 2024.
- Manitoba: National Fire Code of Canada 2020, through the Manitoba Fire Code Regulation, in force since 1 January 2024.
| System | What’s required | How often | Code reference |
|---|---|---|---|
| Sprinklers | Annual inspection and test; 5-year internal pipe check | Every 12 months | 6.4.1.1 · NFPA 25 |
| Fire alarm | Annual inspection and test of the whole system | Every 12 months | 6.3.1.2 · CAN/ULC-S536 |
| Standpipe and hose | Annual inspection; flow test every 5 years | Every 12 months | 6.4.1.1 · NFPA 25 |
| Fire pumps | Annual flow test; weekly or monthly no-flow run | Every 12 months | 6.4.1.1 · NFPA 25 |
| Kitchen suppression | Maintenance at least every 6 months and after any discharge | Every 6 months | 2.6.1.9 · NFPA 96, NFPA 17A |
| Special hazard | Dry chemical every 6 months; others per their standard | Every 6 or 12 months | 6.6.1.1 · NFPA 17, 12, 2001 |
| Fire extinguishers | Monthly inspection; annual maintenance; 6-year and hydrostatic tests | Every 12 months | 6.2.1.1 · NFPA 10 |
| Emergency lighting | Monthly test; annual full-duration test | Every 12 months | 6.5.1.6, 6.5.1.7 |
| Exit signs | Annual check; monthly for battery back-up | Every 12 months | 6.5.1.8 |
| Backflow preventers | Annual test (water utility bylaw) | Every 12 months | CSA B64.10 |
| Private fire hydrants | Annual inspection and flow test | Every 12 months | 6.4.1.1 · NFPA 25 |
| Fire safety plan | Review at intervals not greater than 12 months | Every 12 months | 2.8.2.1.(2) |
This guide summarizes the code. Your local fire department has the final say for your building.
Building in Edmonton? Reports also go to Edmonton Fire Rescue Services.
Source: National Fire Code of Canada 2020 and 2023 Alberta Edition, Part 6 and Article 2.8.2.1; BC Fire Code 2024; NFPA 10, 17, 17A, 25 and 96; CAN/ULC-S536:2019; CSA B64.10.